Taylor 3 Solar Site

Butler, Georgia
Scope of Work

Brad Cole Construction was to develop a lot totaling 887 disturbed acres for the move-on, site preparation, fencing and access road of a solar field in Butler, Georgia,

Details:

  • 254 acres light to heavy clearing and grubbing
  • Installation of 55,468 LF silt fence
  • 80 LF 24” RCP
  • 1,112 LF of 60” RCP with headwalls
  • 574 LF of 6’x4’ box culvert with wing walls
  • 465 LF concrete causeways with cut off walls
  • 4,504,000 CY of cut/fill
  • Installation of acceleration and deceleration lanes
  • Pouring of concrete island
  •  426,000 CY topsoil stripping and respreading